We have recently been working hard to organize the new works and in particular to prepare the projects to appropriate the funds which are still available. The procedures specified in the Code of Public Contracts both for direct commissions under the permitted limit and for tenders are fairly complex and require that we respect very specific phases and time frames. This means that the time that passes between the development of a project and the start of work is relatively long.

Continue reading

Archaeological soundings on the vaults of trajanic galleries 20a and 20b

spessore-volta500

In September-November 2012, we carried out an archaeological sounding in the sector of the Oppian Hill park above the outer surface of Trajanic Galleries 20A and 20B. The study was aimed at understanding the external layout and construction features of the ancient vaults, with a view both to reconstructing the missing parts and to defining the new external protection system for the monument. Below we publish the preliminary results of the archaeological study.

Continue reading

The general project

Disegno ricostruttivo del padiglione della Domus Aurea sul Colle Oppio (H.-J. Beste – DAI)

The first “Conservation Plan for the Monument” (Preliminary project report and definitive project), developed from an idea by A. Vodret, was drawn up by the Soprintendenza Speciale per i Beni Archeologici di Roma in March 2011 and written by F. Filippi, A. Vodret, I. Sciortino, E. Segala and M. Pesce. It was then presented to the Technical Committees for Archaeological, Architectural and Landscape Heritage of the Italian Ministry for Cultural Heritage and Activities (MiBAC). Subsequently, those parts of the project concerning the consolidation of structures and decorations, and the tests for the proposed new arrangement of the waterproof roof were launched.

Continue reading

Structural consolidation in the west wing: north-west corner

Ricostruzione delle geometrie originali della volta-Archivio SSBAR

The conservation work to be carried out in the West Wing, and specifically in the north-western corner of the Domus Aurea, are aimed at tackling the two main goals of intervention on the monument:

  • structural consolidation;
  • the overall isolation of the area to minimize heat transfer with the outside, and thus protect and thermally stabilize the surface layers of the fresco paintings decorating most of the rooms of the Domus.